ANALISIS PENYEBAB PENINGKATAN DURASI REPARASI MT. RATU RUWAIDAH DENGAN FTA DAN FMECA
Abstract
According to Dock News data on repair projects throughout 2022 carried out at PT PAL Indonesia's Dock
shows that the MT Ratu Ruwaidah repair project is the only project that has increased duration, which is
64 days. The purpose of the research is to find out the root cause of the increase in duration, evaluate the
risks, and find out the recommendations for handling. Starting with the Fault Tree Analysis method to
obtain the Minimal Cut Set of the root cause of the increase. Furthermore, determining the Minimal Cut
Set as a failure mode for Severity, Occurrence and Detection assessment by respondents to be processed
in the Failure Modes, Effect and Criticality Analysis method. With the risk treatment matrix, failure modes
can be identified how to handle them. The result of the research is that there are 23 events from the minimum
cut set that are determined as failure modes. In the processing of the Failure Modes, Effect And Criticality
Analysis method, the Pareto diagram stage obtained only 13 priority event/failure mode codes. As a result,
the 13 failure modes occupy the colors red (prevent and mitigate), orange (mitigate) and yellow (prevent)
in the risk treatment matrix.