ANALISIS BIAYA DAN WAKTU PEMBANGUNAN KAPAL ALUMINIUM MENGGUNAKAN METODE EARNED VALUE ANALYSIS (EVA)

Authors

  • Rafidhan Adzimi Jaya Isnadi Politeknik Perkapalan Negeri Surabaya
  • Alma Vita Sophia Politeknik Perkapalan Negeri Surabaya
  • Mirza Ardiana Politeknik Perkapalan Negeri Surabaya

DOI:

https://doi.org/10.33863/mbmc.v4i1.4099

Keywords:

EVA, SPI, CPI, EAC, EAS

Abstract

The aluminum vessel construction project, with a contract value of IDR 743,700,000, experienced
deviations from the initial plan. This study applies the Earned Value Analysis (EVA) method to evaluate
the project’s performance and to forecast its cost and completion time. The analysis at the 12th week
indicated a Cost Performance Index (CPI) of 1.74 (CPI > 1), reflecting cost efficiency, and a Schedule
Performance Index (SPI) of 0.86 (SPI < 1), suggesting a schedule delay. The Estimate to Complete (ETC)
was calculated at IDR 198,035,573, while the Estimate at Completion (EAC) was IDR 427,076,931,
indicating potential cost adjustments at project completion. Furthermore, the Estimate to Schedule (ETS)
of 2.3 projected a total completion duration EAS of 14.3 weeks. These findings demonstrate that the EVA
method provides a comprehensive overview of both cost efficiency and schedule performance, thereby
serving as an effective tool for project monitoring and control.

Downloads

Published

2025-12-01